An estimate is built from cost codes drawn from the central library. The estimate is always organized by Division (the AREMA-aligned sections below) — that structure never changes. Three ways to add work:
| Code | Description | Qty | UOM | L | E | M | S | Cost/U | Mkup | Sell/U | Extended | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01.10.005 | Mobilization Package — Mid Project | 1 | LS | $12,500 | $18,000 | — | — | $30,500 | 18% | $35,990 | $35,990 | |
| 01.10.020 | Demobilization & Site Cleanup | 1 | LS | $4,800 | $3,200 | — | — | $8,000 | 18% | $9,440 | $9,440 | |
| 01.20.010 | Flagging Services — Daily | 45 | DAY | $920 | — | — | — | $920 | 15% | $1,058 | $47,610 | |
| 01.30.010 | Project Supervision | 60 | DAY | $1,150 | — | — | — | $1,150 | 15% | $1,323 | $79,350 | |
| 01.40.010 | Bonds & Insurance Package | 1 | LS | — | — | — | $22,500 | $22,500 | 5% | $23,625 | $23,625 | |
| · | ||||||||||||
| Code | Description | Qty | UOM | L | E | M | S | Cost/U | Mkup | Sell/U | Extended | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 02.10.005 | Clearing & Grubbing | 2.4 | ACRE | $1,800 | $2,400 | — | — | $4,200 | 18% | $4,956 | $11,894 | |
| 02.20.005 | Subgrade Preparation | 1,500 | LF | $4.50 | $6.20 | — | — | $10.70 | 18% | $12.63 | $18,939 | |
| 02.50.005 | Erosion Control Package | 1 | LS | $3,200 | $1,400 | $4,800 | — | $9,400 | 18% | $11,092 | $11,092 | |
| · | ||||||||||||
| Code | Description | Qty | UOM | L | E | M | S | Cost/U | Mkup | Sell/U | Extended | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 04.10.005 | Subballast Placement & Compaction | 1,650 | TON | $4.20 | $5.80 | $18.50 | — | $28.50 | 18% | $33.63 | $55,489 | |
| 04.20.005 | New Ballast Placement (#4 AREMA) | 1,200 | TON | $4.20 | $5.80 | $42.00 | — | $52.00 | 18% | $61.36 | $73,632 | |
| 04.30.005 | Ballast Regulating | 1,500 | LF | $0.80 | $1.40 | — | — | $2.20 | 18% | $2.60 | $3,894 | |
| · | ||||||||||||
| Code | Description | Qty | UOM | L | E | M | S | Cost/U | Mkup | Sell/U | Extended | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05.10.020 | Wood Ties — Hardwood, 7"x9"x8.5' | 825 | EA | — | — | $68.50 | — | $68.50 | 12% | $76.72 | $63,294 | |
| 05.20.040 | Rail Package — 132 RE Relay, CWR | 3,000 | LF | — | — | $38.00 | — | $38.00 | 12% | $42.56 | $127,680 | |
| 05.30.010 | OTM Package — Joints, Anchors, Plates | 1 | LS | — | — | $14,800 | — | $14,800 | 12% | $16,576 | $16,576 | |
| · | ||||||||||||
| Code | Description | Qty | UOM | L | E | M | S | Cost/U | Mkup | Sell/U | Extended | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 06.10.005 | New Track Construction (Panel Build) | 1,500 | LF | $11.20 | $14.50 | — | — | $25.70 | 18% | $30.33 | $45,489 | |
| 06.20.010 | Surface, Line & Dress | 1,500 | LF | $4.20 | $6.80 | — | — | $11.00 | 18% | $12.98 | $19,470 | |
| 06.30.005 | Field Welding — Thermite | 24 | EA | $280 | $95.00 | $320 | — | $695 | 18% | $820 | $19,682 | |
| · | ||||||||||||
| Code | Description | Qty | UOM | L | E | M | S | Cost/U | Mkup | Sell/U | Extended | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 07.10.020 | #10 Turnout — Wood Ties, New, Install | 1 | EA | $14,500 | $9,800 | $38,500 | — | $62,800 | 18% | $74,104 | $74,104 | |
| · | ||||||||||||
| Code | Description | Qty | UOM | L | E | M | S | Cost/U | Mkup | Sell/U | Extended | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 08.10.005 | Asphalt Crossing — 2-Lane Road | 1 | EA | $8,400 | $4,200 | $6,800 | $5,500 | $24,900 | 18% | $29,382 | $29,382 | |
| · | ||||||||||||
| Code | Description | Qty | UOM | L | E | M | S | Cost/U | Mkup | Sell/U | Extended | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 13.30.010 | Project Management Labor | 3 | MO | $12,500 | — | — | — | $12,500 | 12% | $14,000 | $42,000 | |
| · | ||||||||||||