284 line items across 14 divisions · grouped by section · default rates illustrative
This is the full cost code list — every priced row available to estimators, grouped by Division and Section. Three-level numbering: Division.Section.LineItem. Example: 07.10.020 = Division 07 (Turnouts) → Section 10 (Turnout Installation) → Line Item 020 (#10 Turnout, Wood Ties, Relay, Install).
07.10.020 captures a whole turnout install as a single line — quick estimates). Others are atomic components (05.10.005 wood tie, 05.20.025 rail) that combine into assemblies for detailed estimates. The list intentionally supports both modes.| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 01.10.005 | Mobilization Package — Small Project (<$250k) | LS | $18,400 | |
| 01.10.010 | Mobilization Package — Mid Project ($250k–$1M) | LS | $30,500 | |
| 01.10.015 | Mobilization Package — Major Project (>$1M) | LS | $68,200 | |
| 01.10.020 | Demobilization & Site Cleanup | LS | $8,000 | |
| 01.10.025 | Equipment Mobilization — Hi-Rail to Site | EA | $850 | |
| 01.10.030 | Equipment Mobilization — Crane / Heavy | EA | $3,400 | |
| 01.10.035 | Crew Travel Per Diem | DAY | $145 | |
| 01.10.040 | Crew Lodging — per night | NIGHT | $165 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 01.20.005 | Flagging Services — Daily | DAY | $920 | |
| 01.20.010 | Flagging Services — Weekly Block | WK | $4,400 | |
| 01.20.015 | Foreman Flagging Coverage | DAY | $1,180 | |
| 01.20.020 | Roadway Worker Protection (RWP) Setup | LS | $1,500 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 01.30.005 | Project Supervisor — Daily | DAY | $1,350 | |
| 01.30.010 | General Foreman — Daily | DAY | $1,150 | |
| 01.30.015 | Track Foreman — Daily | DAY | $980 | |
| 01.30.020 | Health & Safety Officer — Daily | DAY | $1,050 | |
| 01.30.025 | Quality Control Inspector — Daily | DAY | $1,100 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 01.40.005 | Performance & Payment Bond | % CONTRACT | — | typically 1.0–1.5% |
| 01.40.010 | Builder's Risk Insurance | % CONTRACT | — | typically 0.25–0.5% |
| 01.40.015 | Railroad Protective Liability (RPL) Insurance | LS | $8,500 | |
| 01.40.020 | General Liability Insurance Allocation | LS | $4,200 | |
| 01.40.025 | Pollution Liability Insurance | LS | $3,500 | |
| 01.40.030 | Permits & Right of Entry Fees | LS | $5,500 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 02.10.005 | Clearing & Grubbing | ACRE | $4,200 | |
| 02.10.010 | Tree Removal — Small (<12") | EA | $220 | |
| 02.10.015 | Tree Removal — Large (>12") | EA | $850 | |
| 02.10.020 | Stump Removal & Disposal | EA | $380 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 02.20.005 | Subgrade Preparation | LF | $10.70 | |
| 02.20.010 | Cut & Fill — Light Conditions | CY | $8.50 | |
| 02.20.015 | Cut & Fill — Heavy Conditions | CY | $14.20 | |
| 02.20.020 | Embankment Construction | CY | $12.40 | |
| 02.20.025 | Topsoil Strip & Stockpile | CY | $6.80 | |
| 02.20.030 | Topsoil Replace & Spread | CY | $8.20 | |
| 02.20.035 | Common Excavation | CY | $9.50 | |
| 02.20.040 | Rock Excavation | CY | $38.00 | |
| 02.20.045 | Borrow Material Hauling | CY | $18.50 | |
| 02.20.050 | Compaction (8" lift) | CY | $3.20 | |
| 02.20.055 | Site Restoration & Seeding | SY | $2.80 | |
| 02.20.060 | Final Grading | SY | $1.40 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 02.50.005 | Silt Fence Installation | LF | $4.20 | |
| 02.50.010 | Wattle / Straw Roll | LF | $3.80 | |
| 02.50.015 | Erosion Control Matting | SY | $5.40 | |
| 02.50.020 | Inlet Protection | EA | $285 | |
| 02.50.025 | Stabilized Construction Entrance | EA | $2,400 | |
| 02.50.030 | SWPPP Plan & Compliance | LS | $4,800 | |
| 02.50.035 | Sediment Pond Construction | EA | $8,500 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 03.10.005 | Geotextile Fabric — Woven | SY | $3.40 | |
| 03.10.010 | Geotextile Fabric — Non-Woven | SY | $2.80 | |
| 03.10.015 | Geogrid Reinforcement | SY | $6.20 | |
| 03.10.020 | Lime Stabilization (per 6" lift) | SY | $5.40 | |
| 03.10.025 | Cement Stabilization (per 6" lift) | SY | $7.80 | |
| 03.10.030 | Subgrade Undercut & Replace | CY | $22.50 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 03.20.005 | CMP Culvert — 18" diameter | LF | $48.00 | |
| 03.20.010 | CMP Culvert — 24" diameter | LF | $64.00 | |
| 03.20.015 | CMP Culvert — 36" diameter | LF | $102 | |
| 03.20.020 | CMP Culvert — 48" diameter | LF | $145 | |
| 03.20.025 | CMP Culvert — 60" diameter | LF | $198 | |
| 03.20.030 | RCP Culvert — 24" diameter | LF | $92.00 | |
| 03.20.035 | RCP Culvert — 36" diameter | LF | $138 | |
| 03.20.040 | RCP Culvert — 48" diameter | LF | $184 | |
| 03.20.045 | Headwall — Concrete | EA | $3,800 | |
| 03.20.050 | Endwall — Concrete | EA | $3,500 | |
| 03.20.055 | Underdrain Pipe — 6" | LF | $18.50 | |
| 03.20.060 | Underdrain Pipe — 8" | LF | $22.00 | |
| 03.20.065 | Ditch Excavation | LF | $8.20 | |
| 03.20.070 | Ditch Cleaning | LF | $4.50 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 04.10.005 | Subballast — Place & Compact | TON | $28.50 | |
| 04.10.010 | Subballast — Material Only | TON | $18.50 | |
| 04.10.015 | Subballast — Spread & Grade | TON | $6.80 | |
| 04.10.020 | Subballast Trucking | TON | $5.20 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 04.20.005 | New Ballast — #4 AREMA | TON | $52.00 | |
| 04.20.010 | New Ballast — #4A AREMA | TON | $56.00 | |
| 04.20.015 | Shoulder Ballast | TON | $48.00 | |
| 04.20.020 | Ballast Trucking | TON | $6.50 | |
| 04.20.025 | Spot Ballast (Yard Work) | TON | $65.00 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 04.30.005 | Ballast Regulating | LF | $2.20 | |
| 04.30.010 | Ballast Regulating — per Mile | MILE | $11,500 | |
| 04.30.015 | Crib & Shoulder Cleaning | LF | $4.80 | |
| 04.30.020 | Undercutter Cleaning | LF | $18.50 | |
| 04.30.025 | Shoulder Undercutter | LF | $12.20 | |
| 04.30.030 | Spent Ballast Disposal | TON | $14.00 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 05.10.005 | Wood Tie — Hardwood, 7"x9"x8.5' | EA | $68.50 | |
| 05.10.010 | Wood Tie — Hardwood, 7"x9"x9' | EA | $76.00 | |
| 05.10.015 | Wood Tie — Hardwood, Industrial Grade | EA | $58.00 | |
| 05.10.020 | Concrete Tie — Mainline | EA | $145 | |
| 05.10.025 | Concrete Tie — Industrial | EA | $118 | |
| 05.10.030 | Switch Tie Set — #8 Turnout | SET | $4,200 | |
| 05.10.035 | Switch Tie Set — #10 Turnout | SET | $5,400 | |
| 05.10.040 | Switch Tie Set — #15 Turnout | SET | $8,800 | |
| 05.10.045 | Tie Disposal | EA | $8.50 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 05.20.005 | Rail — 115 RE New, CWR | LF | $72.00 | |
| 05.20.010 | Rail — 115 RE Relay | LF | $32.00 | |
| 05.20.015 | Rail — 132 RE New, CWR | LF | $82.00 | |
| 05.20.020 | Rail — 132 RE Relay | LF | $38.00 | |
| 05.20.025 | Rail — 136 RE New, CWR | LF | $88.00 | |
| 05.20.030 | Rail — 136 RE Relay | LF | $42.00 | |
| 05.20.035 | Rail — 141 AB New, CWR | LF | $95.00 | |
| 05.20.040 | Rail — Stick Rail (39') | EA | $3,400 | |
| 05.20.045 | Compromise Joint Bar | EA | $320 | |
| 05.20.050 | Rail Cropping & Disposal | LF | $4.50 | |
| 05.20.055 | Rail Trucking | LF | $1.80 | |
| 05.20.060 | Rail Storage & Handling | LF | $0.85 | |
| 05.20.065 | Rail Inspection | LF | $0.45 | |
| 05.20.070 | Rail Saw & Drill Setup | LS | $1,200 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 05.30.005 | Tie Plate — Single Shoulder | EA | $18.50 | |
| 05.30.010 | Tie Plate — Double Shoulder | EA | $24.00 | |
| 05.30.015 | Cut Spike | KEG | $145 | |
| 05.30.020 | Track Bolt | EA | $4.20 | |
| 05.30.025 | Joint Bar — Standard | EA | $85.00 | |
| 05.30.030 | Insulated Joint Bar | EA | $380 | |
| 05.30.035 | Rail Anchor — Box | EA | $5.20 | |
| 05.30.040 | Rail Anchor — Spring | EA | $6.80 | |
| 05.30.045 | Pandrol e-Clip | EA | $3.40 | |
| 05.30.050 | Pandrol Shoulder | EA | $8.20 | |
| 05.30.055 | OTM Bulk Package — Mile equivalent | LS | $18,500 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 06.10.005 | New Track Construction — Panel Build | LF | $25.70 | |
| 06.10.010 | Track Laying — Direct Spike (Wood Ties) | LF | $18.40 | |
| 06.10.015 | Track Laying — Pandrol Fasteners | LF | $22.80 | |
| 06.10.020 | Industry Track Tie-In | LS | $38,500 | |
| 06.10.025 | Yard Track Construction | LF | $32.00 | |
| 06.10.030 | Siding Extension | LF | $28.50 | |
| 06.10.035 | Track Removal & Salvage | LF | $14.20 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 06.20.005 | Surface, Line & Dress — per LF | LF | $11.00 | |
| 06.20.010 | Surface, Line & Dress — per Mile | MILE | $41,800 | |
| 06.20.015 | Spot Surfacing | LF | $18.00 | |
| 06.20.020 | Switch Surfacing | EA | $2,400 | |
| 06.20.025 | Bridge Approach Surfacing | LF | $28.00 | |
| 06.20.030 | Crossing Approach Surfacing | LF | $24.00 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 06.30.005 | Field Welding — Thermite | EA | $695 | |
| 06.30.010 | Field Welding — Flash Butt | EA | $480 | |
| 06.30.015 | Plant Welding | EA | $380 | |
| 06.30.020 | Weld Repair / Re-do | EA | $850 | |
| 06.30.025 | Rail Anchor Application | PAIR | $14.50 | |
| 06.30.030 | Rail De-stress / Adjust | LF | $3.80 | |
| 06.30.035 | Spike Re-spike | LF | $4.20 | |
| 06.30.040 | Rail Lubrication | LF | $0.95 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 07.10.005 | #8 Turnout — Wood Ties, New, Install | EA | $48,200 | |
| 07.10.010 | #8 Turnout — Wood Ties, Relay, Install | EA | $30,500 | |
| 07.10.015 | #10 Turnout — Wood Ties, New, Install | EA | $62,800 | |
| 07.10.020 | #10 Turnout — Wood Ties, Relay, Install | EA | $38,500 | |
| 07.10.025 | #11 Turnout — Wood Ties, New, Install | EA | $71,400 | |
| 07.10.030 | #11 Turnout — Wood Ties, Relay, Install | EA | $44,200 | |
| 07.10.035 | #14 Turnout — Wood Ties, New, Install | EA | $84,500 | |
| 07.10.040 | #15 Turnout — Wood Ties, New, Install | EA | $92,800 | |
| 07.10.045 | #20 Turnout — Concrete Ties, New, Install | EA | $148,200 | |
| 07.10.050 | Crossover Installation — #10 Pair | LS | $138,500 | |
| 07.10.055 | Turnout Removal & Salvage | EA | $14,500 | |
| 07.10.060 | Spring Switch Installation | EA | $18,500 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 07.20.005 | Switch Point Renewal | EA | $4,800 | |
| 07.20.010 | Frog — Rigid (RBM) | EA | $5,400 | |
| 07.20.015 | Frog — Spring | EA | $7,200 | |
| 07.20.020 | Frog — Self-Guarded | EA | $6,500 | |
| 07.20.025 | Frog Replacement Labor | EA | $3,800 | |
| 07.20.030 | Switch Stand | EA | $2,400 | |
| 07.20.035 | Switch Throw Mechanism | EA | $3,200 | |
| 07.20.040 | Guard Rail — Standard | LF | $48.00 | |
| 07.20.045 | Switch Tie Replacement — Out-of-Face | EA | $165 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 07.30.005 | Derail — Hinged | EA | $4,200 | |
| 07.30.010 | Derail — Sliding | EA | $5,800 | |
| 07.30.015 | Bumping Post — Standard | EA | $3,400 | |
| 07.30.020 | Bumping Post — Heavy Duty | EA | $5,200 | |
| 07.30.025 | Wheel Stop | EA | $1,800 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 08.10.005 | Asphalt Crossing — 2-Lane Road | EA | $24,900 | |
| 08.10.010 | Asphalt Crossing — 4-Lane Highway | EA | $48,500 | |
| 08.10.015 | Concrete Panel Crossing — Standard | EA | $38,400 | |
| 08.10.020 | Concrete Panel Crossing — Heavy Duty | EA | $52,800 | |
| 08.10.025 | Rubber Panel Crossing | EA | $52,800 | |
| 08.10.030 | Timber Plank Crossing — Private | EA | $14,500 | |
| 08.10.035 | Crossing Demolition & Removal | EA | $6,800 | |
| 08.10.040 | Crossing Approach Resurfacing | LF | $28.00 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 08.20.005 | Crossbuck Sign | EA | $850 | |
| 08.20.010 | Stop Sign Package | EA | $480 | |
| 08.20.015 | Yield Sign Package | EA | $420 | |
| 08.20.020 | Pavement Markings | LS | $1,800 | |
| 08.20.025 | Active Warning Coordination (sub-managed) | LS | $4,500 | |
| 08.20.030 | Pedestrian Crossing Package | EA | $12,500 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 09.10.005 | Timber Tie — Bridge | EA | $285 | |
| 09.10.010 | Timber Stringer — 8x16 | EA | $1,840 | |
| 09.10.015 | Timber Stringer — 8x18 | EA | $2,180 | |
| 09.10.020 | Timber Cap — 12x14 | EA | $1,650 | |
| 09.10.025 | Timber Cap — 14x14 | EA | $1,980 | |
| 09.10.030 | Timber Pile — Splice | EA | $2,800 | |
| 09.10.035 | Timber Pile — Replace | EA | $4,500 | |
| 09.10.040 | Bridge Deck — Open Deck | LF | $285 | |
| 09.10.045 | Bridge Deck — Ballast Deck | LF | $320 | |
| 09.10.050 | Bridge Walkway | LF | $65.00 | |
| 09.10.055 | Bridge Handrail | LF | $48.00 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 09.20.005 | Concrete Repair — Spalling Patch | SF | $48.00 | |
| 09.20.010 | Concrete Repair — Crack Injection | LF | $32.00 | |
| 09.20.015 | Joint Sealing | LF | $18.00 | |
| 09.20.020 | Pier Repair — Cap Replacement | EA | $28,500 | |
| 09.20.025 | Abutment Repair | LS | $38,000 | |
| 09.20.030 | Box Culvert — Precast Install | EA | $24,500 | |
| 09.20.035 | Box Culvert Extension | LF | $580 | |
| 09.20.040 | Cathodic Protection | LS | $18,500 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 09.30.005 | Steel Bridge Painting — Spot | SF | $28.00 | |
| 09.30.010 | Steel Bridge Painting — Full | SF | $14.50 | |
| 09.30.015 | Rivet Replacement | EA | $165 | |
| 09.30.020 | Bolt Replacement | EA | $45.00 | |
| 09.30.025 | Steel Member Replacement | TON | $8,500 | |
| 09.30.030 | Bearing Repair | EA | $4,800 | |
| 09.30.035 | Steel Inspection | LS | $5,500 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 10.10.005 | Tie R&R — Spot Replacement | EA | $105 | |
| 10.10.010 | Tie R&R — Out-of-Face | EA | $88.00 | |
| 10.10.015 | Surfacing — per Mile | MILE | $41,800 | |
| 10.10.020 | Surfacing — per LF | LF | $11.00 | |
| 10.10.025 | Track Patrol — per Shift | SHIFT | $980 | |
| 10.10.030 | Visual Track Inspection | MILE | $285 | |
| 10.10.035 | Vegetation Control — Spray | MILE | $1,240 | |
| 10.10.040 | ROW Mowing | MILE | $850 | |
| 10.10.045 | Brush Cutting | MILE | $2,400 | |
| 10.10.050 | Switch Cleaning & Lubrication | EA | $145 | |
| 10.10.055 | Joint Tightening | EA | $28.00 | |
| 10.10.060 | Gauge Restraint Test | MILE | $580 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 10.20.005 | Emergency Response Mobilization | LS | $8,500 | |
| 10.20.010 | Derailment Re-rail Package | LS | $28,500 | |
| 10.20.015 | Storm Damage Response — Daily | DAY | $12,500 | |
| 10.20.020 | Snow & Ice Removal — per Shift | SHIFT | $4,800 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 11.10.005 | Production Tamper | DAY | $3,800 | |
| 11.10.010 | Switch & Production Tamper | DAY | $4,200 | |
| 11.10.015 | Spot Tamper | DAY | $2,400 | |
| 11.10.020 | Ballast Regulator | DAY | $2,800 | |
| 11.10.025 | Tie Inserter | DAY | $3,400 | |
| 11.10.030 | Tie Crane | DAY | $2,800 | |
| 11.10.035 | Spike Puller | DAY | $1,800 | |
| 11.10.040 | Spike Driver | DAY | $1,800 | |
| 11.10.045 | Anchor Machine | DAY | $2,200 | |
| 11.10.050 | Rail Saw | DAY | $850 | |
| 11.10.055 | Rail Drill | DAY | $850 | |
| 11.10.060 | Rail Heater | DAY | $1,400 | |
| 11.10.065 | Track Loader | DAY | $1,800 | |
| 11.10.070 | Undercutter | DAY | $5,400 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 11.20.005 | Hi-Rail Pickup | DAY | $380 | |
| 11.20.010 | Hi-Rail Excavator | DAY | $2,400 | |
| 11.20.015 | Hi-Rail Crane (Speed Swing) | DAY | $2,800 | |
| 11.20.020 | Hi-Rail Boom Truck | DAY | $1,800 | |
| 11.20.025 | Backhoe | DAY | $850 | |
| 11.20.030 | Excavator (Tracked) | DAY | $1,400 | |
| 11.20.035 | Skid Steer | DAY | $480 | |
| 11.20.040 | Generator & Light Plant | DAY | $285 | |
| 11.20.045 | Welding Truck | DAY | $950 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 11.30.005 | Crawler Crane | DAY | $4,800 | |
| 11.30.010 | Truck-Mounted Crane | DAY | $2,400 | |
| 11.30.015 | Railbound Crane | DAY | $5,800 | |
| 11.30.020 | Front-End Loader | DAY | $1,200 | |
| 11.30.025 | Dump Truck | DAY | $850 | |
| 11.30.030 | Lowboy & Trucking — per Move | EA | $1,800 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 12.10.005 | Signal & Communications — Crossing System | LS | $185,000 | |
| 12.10.010 | Signal & Communications — Switch Circuit | EA | $18,500 | |
| 12.10.015 | Signal Maintainer — Daily | DAY | $1,400 | |
| 12.10.020 | Welding Sub — per Weld | EA | $720 | |
| 12.10.025 | Survey — Centerline & Profile | MILE | $8,500 | |
| 12.10.030 | Survey — As-Built | LS | $12,500 | |
| 12.10.035 | Geotechnical / Soils Investigation | LS | $18,500 | |
| 12.10.040 | Environmental / SWPPP Sub | LS | $8,500 | |
| 12.10.045 | Engineering / Design Sub | LS | $28,500 | |
| 12.10.050 | Trucking & Hauling Sub | HR | $145 | |
| 12.10.055 | Demolition Sub | LS | — | |
| 12.10.060 | Concrete Sub (Bridges/Structures) | LS | — |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 13.10.005 | Performance Bond | % CONTRACT | — | typically 0.75–1.25% |
| 13.10.010 | Payment Bond | % CONTRACT | — | typically 0.25–0.5% |
| 13.10.015 | Bid Bond | % BID | — | typically 0.05–0.10% |
| 13.10.020 | Maintenance Bond | % CONTRACT | — | post-completion, ~1 yr |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 13.20.005 | General Liability | LS | $4,200 | |
| 13.20.010 | Workers' Compensation | % PAYROLL | — | varies by state / class code |
| 13.20.015 | Builder's Risk | % CONTRACT | — | typically 0.25–0.5% |
| 13.20.020 | Pollution Liability | LS | $3,500 | |
| 13.20.025 | Railroad Protective Liability (RPL) | LS | $8,500 | |
| 13.20.030 | Auto Liability Allocation | LS | $1,800 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 13.30.005 | Project Manager — Monthly | MO | $12,500 | |
| 13.30.010 | Estimator — Hourly | HR | $145 | |
| 13.30.015 | Site Office & Trailer — Monthly | MO | $2,800 | |
| 13.30.020 | Field Office Operations — Monthly | MO | $1,800 | |
| 13.30.025 | Document Control — Monthly | MO | $2,200 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 14.10.005 | Design Contingency | % COST | — | typically 5–10% |
| 14.10.010 | Construction Contingency | % COST | — | typically 5–10% |
| 14.10.015 | Owner's Contingency | % COST | — | typically 5% |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 14.20.005 | Home Office Overhead | % COST | — | typically 8–12% |
| 14.20.010 | General & Administrative | % COST | — | typically 3–6% |
| 14.20.015 | Profit / Margin | % COST | — | typically 8–15% |
| 14.20.020 | Bond Premium Pass-Through | % CONTRACT | — | if not in 01.40 |
| Code | Description | UOM | Default Rate | Notes |
|---|---|---|---|---|
| 14.30.005 | State Sales Tax | % MATERIAL | — | varies by state |
| 14.30.010 | Use Tax | % MATERIAL | — | varies by jurisdiction |
| 14.30.015 | City / Local Tax | % CONTRACT | — | if applicable |