How This Estimate is Built

An estimate is built from cost codes drawn from the central library. The estimate is always organized by Division (the AREMA-aligned sections below) — that structure never changes. Three ways to add work:

1. Add Line Item
Pulls one priced row directly. Best for single charges (flagging days) or aggregate codes (a whole turnout as a single lump-sum line — see Section 07 below). No assembly tag, no header — it just lives in its section.
2. Add Assembly
Drops a pre-built bundle of line items at once. Each component lands in its natural division (a turnout assembly puts ties under Track Materials, frog under Turnouts, ballast under Ballast). Lines carry an assembly tag for grouping, editing, or removing them together.
3. Add Section
Adds a whole new section to the estimate (e.g. add Bridges if your scope includes bridge work). Sections come from the standard 14 divisions — you only include the ones relevant to the project.
The estimate's structure stays consistent
Whether you add a single line, an assembly, or a whole section — the estimate's top-level structure is always the same 14-division AREMA framework. Assemblies don't create their own "sub-headers" in the estimate. Instead, each assembly-derived line carries metadata (an assembly tag) that powers an optional Group by Assembly view toggle for review.
CodeDescriptionQtyUOMLEMSCost/UMkupSell/UExtended
01.10.005
Mobilization Package — Mid Project
1LS$12,500$18,000$30,50018%$35,990$35,990
01.10.020
Demobilization & Site Cleanup
1LS$4,800$3,200$8,00018%$9,440$9,440
01.20.010
Flagging Services — Daily
45DAY$920$92015%$1,058$47,610
01.30.010
Project Supervision
60DAY$1,150$1,15015%$1,323$79,350
01.40.010
Bonds & Insurance Package
1LS$22,500$22,5005%$23,625$23,625
·
CodeDescriptionQtyUOMLEMSCost/UMkupSell/UExtended
02.10.005
Clearing & Grubbing
2.4ACRE$1,800$2,400$4,20018%$4,956$11,894
02.20.005
Subgrade Preparation
1,500LF$4.50$6.20$10.7018%$12.63$18,939
02.50.005
Erosion Control Package
1LS$3,200$1,400$4,800$9,40018%$11,092$11,092
·
CodeDescriptionQtyUOMLEMSCost/UMkupSell/UExtended
04.10.005
Subballast Placement & Compaction
1,650TON$4.20$5.80$18.50$28.5018%$33.63$55,489
04.20.005
New Ballast Placement (#4 AREMA)
1,200TON$4.20$5.80$42.00$52.0018%$61.36$73,632
04.30.005
Ballast Regulating
1,500LF$0.80$1.40$2.2018%$2.60$3,894
·
CodeDescriptionQtyUOMLEMSCost/UMkupSell/UExtended
05.10.020
Wood Ties — Hardwood, 7"x9"x8.5'
825EA$68.50$68.5012%$76.72$63,294
05.20.040
Rail Package — 132 RE Relay, CWR
3,000LF$38.00$38.0012%$42.56$127,680
05.30.010
OTM Package — Joints, Anchors, Plates
1LS$14,800$14,80012%$16,576$16,576
·
CodeDescriptionQtyUOMLEMSCost/UMkupSell/UExtended
06.10.005
New Track Construction (Panel Build)
1,500LF$11.20$14.50$25.7018%$30.33$45,489
06.20.010
Surface, Line & Dress
1,500LF$4.20$6.80$11.0018%$12.98$19,470
06.30.005
Field Welding — Thermite
24EA$280$95.00$320$69518%$820$19,682
·
CodeDescriptionQtyUOMLEMSCost/UMkupSell/UExtended
07.10.020
#10 Turnout — Wood Ties, New, Install
1EA$14,500$9,800$38,500$62,80018%$74,104$74,104
·
CodeDescriptionQtyUOMLEMSCost/UMkupSell/UExtended
08.10.005
Asphalt Crossing — 2-Lane Road
1EA$8,400$4,200$6,800$5,500$24,90018%$29,382$29,382
·
CodeDescriptionQtyUOMLEMSCost/UMkupSell/UExtended
13.30.010
Project Management Labor
3MO$12,500$12,50012%$14,000$42,000
·
Cost Total
$701,898
Sell Total
$808,633
Margin
13.2%
Contingency
5.0%
Final Bid
$849,065
LibraryManage →
#8 Turnout — Wood Ties, New, Install
ASM-07-001 · 8 items · EA
Sell: $56,900
#10 Turnout — Wood Ties, New, Install
ASM-07-002 · 8 items · EA
Sell: $74,100
#10 Turnout — Wood Ties, Relay, Install
ASM-07-003 · 7 items · EA
Sell: $45,400
#11 Turnout — Wood Ties, New, Install
ASM-07-004 · 8 items · EA
Sell: $84,300
#15 Turnout — Wood Ties, New, Install
ASM-07-005 · 9 items · EA
Sell: $109,500
#20 Turnout — Concrete Ties, New, Install
ASM-07-006 · 10 items · EA
Sell: $174,900
Crossover Installation — #10 Pair
ASM-07-010 · 14 items · LS
Sell: $163,400
Asphalt Crossing — 2-Lane Road
ASM-08-001 · 6 items · EA
Sell: $29,400
Concrete Panel Crossing — Standard
ASM-08-002 · 5 items · EA
Sell: $45,300
Rubber Panel Crossing
ASM-08-003 · 5 items · EA
Sell: $62,300
New Track Construction — Panel Build
ASM-06-001 · 6 items · LF
Sell: $30.30
Tie R&R — Out-of-Face
ASM-06-002 · 5 items · EA
Sell: $104
Surface, Line & Dress — per mile
ASM-06-003 · 4 items · MILE
Sell: $49,300
Timber Bridge Tie Renewal — Out-of-Face
ASM-09-001 · 7 items · EA
Sell: $336
Timber Stringer Replacement
ASM-09-002 · 6 items · EA
Sell: $2,172
Tie R&R — Spot Replacement
ASM-10-001 · 4 items · EA
Sell: $124
Vegetation Control — Spray
ASM-10-002 · 3 items · MILE
Sell: $1,465
Emergency Response Mobilization
ASM-10-003 · 4 items · LS
Sell: $10,030
Mobilization — Small Project (<$250k)
ASM-01-001 · 5 items · LS
Sell: $21,700
Mobilization — Mid Project ($250k–$1M)
ASM-01-002 · 6 items · LS
Sell: $36,000
Demo note: Each line shows the four cost buckets (Labor / Equipment / Material / Sub) feeding both the internal cost and customer-facing sell price. Drag from the Library rail to drop assemblies in. Stale lines flag when the library has updated — refresh per line, section, or whole estimate.